This is the typical flow of activities to design and install your solar power system and receive
state rebates:
1. Complete SolarQuoteTM
a. Design your system for your home using SolarQuoteTM
b. Submit your request at the completion of your quote
b. Submit your request at the completion of your quote
2. We will contact you for a site visit
a. We will revise your quote taking into account any unforeseen installation
issues and incorrect or incomplete data from your SolarQuoteTM.
b. We will complete the site visit by delivering a contract with that revised quote.
b. We will complete the site visit by delivering a contract with that revised quote.
3. Energy Audit
a. In order to receive a CSI rebate an energy audit must be completed.
4. Once you sign the contract
a. We will initiate a permit request.
b. We will initiate a net-metering agreement with your utility.
c. We will start the application for state incentives and reserved future rebate funding.
b. We will initiate a net-metering agreement with your utility.
c. We will start the application for state incentives and reserved future rebate funding.
5. Installation of your solar power system
a. On days that you agree upon, we will install, test and inspection your system,
typically taking 3 days to complete.
b. At the completion, local officials will also complete their own inspection.
b. At the completion, local officials will also complete their own inspection.
6. Paperwork complete
a. Once your utility agrees with net-metering, you can begin producing your own electricity.
b. If a CSI EPBB rebate was choosen you will recieve a one time rebate. If you choose a CSI PBI rebate you will receive monthly rebates for 5 years.
b. If a CSI EPBB rebate was choosen you will recieve a one time rebate. If you choose a CSI PBI rebate you will receive monthly rebates for 5 years.
7. In 6 months
a. We will perform a six month checkup ensuring both safety and system performance.